淡江大橋大事記
Danjiang Bridge milestones


1998  完成規劃報告
Completion of planning report

1999  有條件通過環境影響評估
Conditional passage of EIA

2000年  改採政府編列預算方式辦理

Change to implementation with a government budget

2006  規劃檢討作業

Planning review tasks

2013  通過第1次環境影響差異分析啟動環境監測

Passes first environmental impact discrepancy analysis; initiation of environmental monitoring

2014  「淡江大橋及其連絡道路建設計畫」核定

委託淡江大橋第三標專案管理PCM林同棪工程顧問公司辦理第3標(主橋段)橋型評選等作業

先行辦理對生態、環境及文化資產較無影響,且無用地問題路段之設計施工,以加速推動本計畫

成立環境保護監督小組

「淡江大橋及其連絡道路新建工程」1開工

The "Danjiang Bridge and its access road construction plan" is approved

Hiring of the T.Y. Lin Engineering Consultants Co., Ltd. to conduct bridge type selection tasks etc. for the 3rd tender (main bridge section).

To accelerate project progress, preliminary implementation of design and construction work for sections where there are no impacts on ecology, environment, or cultural assets, and no available land problems.

Establishment of an environmental protection supervisory team

Start of work on the "Construction of Danjiang Bridge and Connecting Road Network" (1st tender)

2015年  完成國際競圖作業

辦理水中、陸域文化資產調查計畫及3項生態研究計畫

辦理八里端及淡水端連絡道工程設計

Completion of international drawing competition tasks

Implementation of an aquatic and terrestrial cultural asset survey project and three ecological research projects.

Implementation of engineering design for access roads on the Bali and Tamsui sections.

2016年  ‧「淡江大橋及其連絡道路新建工程」1完工

「淡江大橋及其連絡道路新建工程」2開工

Completion of the "Construction of Danjiang Bridge and Connecting Road Network" (1st tender)

Start of work on the "Construction of Danjiang Bridge and Connecting Road Network" (2nd tender)

2017  通過第2次環境影響差異分析橋型確定

Passage of 2nd environmental impact discrepancy analysis (confirmation of bridge type)

2018年  ‧行政院核定「淡江大橋及其連絡道路建設計畫」修正

「淡江大橋及其連絡道路新建工程」3決標簽約

The Executive Yuan approves the revised "Danjiang Bridge and its Access Road Construction plan"

Award of tender and contract signing for the "Construction of Danjiang Bridge and Connecting Road Network" (3rd tender)

2019  「淡江大橋及其連絡道路新建工程」3開工
Start of work on "Construction of Danjiang Bridge and Connecting Road Network" (3rd tender)

2021  預計「淡江大橋及其連絡道路新建工程」2完工
Expected completion of the "Construction of Danjiang Bridge and Connecting Road Network" (2nd tender)

2024  預計全線完工通車
Expected completion and opening of full route